Site icon The Legal Co., Ltd.

EEC: Consolidated Draft Notification on Private and Public-Private Investment

green cargo boat beside dock

Photo by Tom Fisk on Pexels.com

EEC: Consolidated Draft Notification on Private and Public-Private Investment

The Eastern Economic Corridor Office (EECO) has released for public hearing a comprehensive Draft Notification of the Eastern Economic Corridor Policy Committee titled “Criteria, Procedures and Conditions for Joint Investment with the Private Sector or for Allowing the Private Sector to be the Investor B.E. .…” (“Notification”).

Upon final promulgation, this single new Notification will repeal and replace all seven earlier versions issued between 2017 and 2020, thereby establishing a modern, unified and fully consolidated regulatory framework for every public-private partnership (PPP) and pure private-investment project in the Eastern Economic Corridor (EEC).

Current Challenges the Draft Seeks to Resolve:

The existing regime has suffered from:

How the New Draft Will Help:

The consolidated Notification introduces a clearer, faster, and more robust system:

1.  One single rulebook aligned with the Public-Private Partnership Act B.E. 2562 (2019) and international best practice.

2.  Strict timelines: 15 days for most completeness checks and agency comments; 30 days for Attorney-General review of contracts and amendments.

3.  Mandatory independent committees appointed by the EEC Policy Committee:

4.  Enhanced transparency and anti-corruption measures:

5.  Explicit value-for-money and risk-allocation requirements in every feasibility study.

6.  Tiered contract-amendment procedure (minor → material → affecting Cabinet-approved principles) with corresponding approval levels.

7.  Obligation, at least five years before expiry, to prepare and obtain approval for a post-concession strategy (re-tender, state takeover, or extension).

8.  Competitive bidding as the unequivocal default; any non-bidding method requires detailed justification and prior Policy Committee approval.

Core Requirements and Procedural Stages:

1.  Project Proposal and Approval

2.  Private Investor Selection

3.  Supervision and Monitoring

4.  Transparency, Consultation and Reporting

Who Will Benefit:

Preparations Required:

Government agencies planning EEC projects should now:

Private investors and consortiums should:

The draft is currently open for public hearing. Following the incorporation of stakeholder comments and publication in the Government Gazette, it will become the exclusive governing regulation for all future EEC investment projects, delivering a markedly more transparent, efficient, and investor-friendly environment for Thailand’s flagship economic corridor.

Author: Panisa Suwanmatajarn, Managing Partner.

Other Articles

Exit mobile version